Road Construction Updates
Contractors for the sewer district will need to close Bluff Road at Gentile Street for some sewer main work. The closure should be as follows:
Thursday Oct 23 at 6:00 AM to end of day possibly 10:00 PM
Friday Oct 24 at 6:00 AM to end of day possibly 10:00 PM


Westbound travel on Gentile may continue westbound through the intersection, then detour north on 2000 West to the six-way roundabout.
Eastbound travel on Gentile may continue eastbound on Gentile.
Northbound and southbound at the intersection will be block
RANCHETTES WEST SUBDIVISION (4/18/18)



Preparing for paving on 3400 West, 2200 South, 2050 South and 1850 South. If weather conditions and road base compactions are favorable, paving operations will begin Friday on 2200 S and 3400 W and continue into next week.

 

Working on utilities at 1850 South.

 

There will be a change in the stop sign configuration at the intersection of 2200 S and 3400 W in the next couple of weeks. The reason for the change is due to traffic patterns that have been and will continue to change as the street network expands throughout this area.

 

As roads become paved, mail delivery to your mailbox is expected to resume, but not until the USPS makes the determination. Mail delivery will continue as it is unless you get a notice either in your temporary mailbox or at your door giving you instructions on where you will begin picking up your mail.


Reminder---Current building code P2903.4.1 requires all water heaters have an expansion tank installed in the event a water heater experiences increased pressures.  With the installation of the backflow prevention device, any water heater which does not have an expansion tank installed has a potential of failing. Please make sure your water heater is brought up to current building code.





Temporary mailboxes are located at the intersection of Doral Street and 2200 South. These are available for those inside the active construction zone. Keys are available at USPS in Clearfield. As construction progresses to other sections of the neighborhood, the use of the temporary mailboxes will switch to those who are inside the active construction area. A notice will be delivered to those residents who will be affected by this change. On the last day of mail delivery to those currently using the temporary mailbox, a notice will be placed in the mailbox to return the key to the Clearfield post office and pick up your mail there prior to resuming delivery to your individual mailbox at your home.

 This project will include replacement of all city infrastructure under the road, as well as the road and sidewalk ramps. This project will continue throughout all of 2018. For email notifications, send an email to projectupdates@syracuseut.com


Melanie Lane (3/21/18)
Sewer main installation has begun. This road is closed to through traffic, but open to traffic accessing the homes inside the immediate construction area. Detour around to Marilyn Drive.


Bluff and Gentile (3/21/18)
Construction of waterlines has begun. one lane of traffic is open with flaggers during construction. Construction is progressing beginning at 1000 West intersection toward Gentile Street. Please be patient and watch for flaggers. Use caution while driving around the construction equipment.




2000 West (SR-108) 300 North to 1700 South (Updated 4/9/18)
Though roadway construction in 2017 will be limited to the area between Heritage Parkway and 300 North, utility companies are on site to relocate their utilities throughout the project area.

Two lanes of through traffic will remain open during daytime hours. However, short term asphalt patching may require some turn lane restrictions in some areas.

Areas Between 470 North and 1275 South  
Rocky Mountain Power, North Davis Sewer District and Century Link will be doing utility work over the next several weeks. Home demolition may take place north of SR-193. Tree removals may also be taking place along the corridor.  Intermittent daytime shoulder closures/turn lane restrictions may occur.

Areas Near the 700 South Intersection 
Night work is scheduled to continue through late-April (9:00 PM - 6:00 AM).  Due to heavy daytime traffic, new utility crossings in and around this intersection must be done at night. Nighttime traffic may be limited to one lane with flaggers. Residents should expect an increase in noise.  Irrigation work at 700 South will be completed by Friday.

Safety 
For your safety and the safety of those working in the area, please exercise caution, stay alert and be prepared for changing lane configurations. We are committed to a safe project and are constantly on alert. 

Questions?  Please feel free to contact us at 844.200.0937 or 801.336.6977.



2000 West Project Logo

2000 West Project Update - April 5, 2018

Construction Activities This Week: 04/05/18 - 04/12/18

  • Crews continue night work in the 2000 West and 300 North intersection and are scheduled to continue through Friday morning, April 6. 
  • Intermittent asphalt paving may take place along the corridor from 300 North to Antelope Drive as crews patch pipe trenches.  Lane shifts and shoulder closures may occur.  
  • Construction crews are scheduled to restripe project corridor areas near 300 North and 2000 West on April 10, 8:00 AM - 3:00 PM.  Please be aware and watch for Sheriff, construction personnel and signage.
  • Extensive utility work continues on the east side of 2000 West from SR-193 to 300 North and will continue through Spring 2018. For those wanting to access 2000 West from the east side of this section, suggested routes include 300 North or SR-193. Avoid taking 150 North, 100 North, and 75 South if possible, but when using these roads, please utilize the dirt ramps onto 2000 West and do not travel down the work zone.
  • Continuing through Spring 2018, utility crews will be working on pipe installation, signal lights, phone, and gas lines from 1275 South to Heritage Parkway, on the west side of 2000 West. Excavation operations are currently underway in this area. To accommodate this work, there will be intermittent closures at 1100 South, 1175 South, and 1275 South.
  • Utility companies continue working throughout the project area between Antelope Drive and 300 North.
  • Intermittent pipe placement and utility work will continue, weather permitting, throughout Spring 2018. Intermittent lane shifts and shoulder closures may occur during these times, so please be aware and watch for signage.

Temporary Access Closure
Construction crews continue utility work from Antelope Drive to 1275 South, on the west side of 2000 West.  To accommodate this work, the business access to Fiiz/Wendy's/Walmart/etc. on 2000 West is temporarily closed. The closure will continue through Thursday, April 5. The access will also be closed Monday, April 9 to allow crews to repave the area.

All businesses in the area may still be accessed via all available entrance points off Antelope Drive.

Long-Term Closure of Access Point Coming this Summer
The business access to Fiiz/Wendy's/Walmart/etc. on 2000 West will be closed from June 1 thru August 17 to allow crews to expedite the work needed between the Elementary and Junior High School over the summer, when school is not in session. Additional details to be announced.


Utility Shutoffs
Utility companies may schedule intermittent shutoffs to accomplish their work. They will provide advance notice where applicable.    


Traffic Alerts

  • To accommodate the utility work between SR-193 and 300 North, there will be intermittent closures at 150 North, 100 North, and 75 South.
  • No parking is allowed within 50 feet of the newly installed HAWK Signal near Syracuse Elementary and Syracuse Jr. High.
  • Intermittent turn lane, shoulder, and median restrictions may occur. 
  • Intermittent lane shifts may occur for utility work and pipe placement through Spring 2018.

West Point Batch Plant Operations
The West Point Batch Plant near 75 North and 2000 West in West Point has been shut down. It is expected to resume operations April 16, 2018.

Safety  
For your safety and the safety of those working in the area, please exercise caution, stay alert, and reduce speeds.

QUESTIONS? CONCERNS?

Email: 2000West@utah.gov
Hotline: 844.200.0937 - 801.336.6977 
Website: www.udot.utah.gov/sr108

Project Background
 

SR-108, also known as 2000 West, is a very busy north-south highway in Davis County, carrying as many as nearly 18,000 vehicles per day.  With the expected growth in population, homes and jobs, this number is expected to double by 2040.  To address this need, UDOT conducted an environmental study from 2006 to 2008 to evaluate various transportation options.  Through careful analysis and close coordination with the communities, a solution was identified that meets the transportation need while minimizing impacts.


The proposed solution was to widen the roadway to two lanes in each direction with a center turn lane.  In April of 2015, UDOT secured funding for a two-mile segment of the project from SR-127 (Syracuse Road) to 300 North in West Point. UDOT looks forward to this opportunity to serve your communities by providing improved transportation and increased safety for all who travel and live around the SR-108 corridor.