Road Construction Updates
700 South (2500 West to St Andrews Drive)
Construction is in progress with piping the ditch between 3000 West and the trail crossing.  Ramps at the trail crossing are being installed, so please follow the detour around it. Installation of a pipeline will along the south edge of the road between 2500 W and 3000 W is currently in progress. Construction will continue through the summer with curb, gutter, and sidewalk and new asphalt having an anticipated completion mid-August.



2500 West (700 South to 1700 South)
Asphalt replacement is progressing between 700 South and 1175 South. The north half mile of road (700 S to 1175 S) will be installed the week of May 6. The sewer main on the south half mile (1175 S to 1700 S) will begin the week of May 13. Construction will continue through the summer with curb, gutter, and sidewalk and new asphalt having an an anticipated completion mid-August.



1000 West (2700 South to Bluff) and 3300 South (1000 West to 930 West)

Construction has begun with pipeline installations. Construction will continue through the spring with new asphalt completed by the end of June. Roads will be closed during the day during construction and open at nights to local traffic. Please use caution and follow all signs while driving through construction zones. Currently construction is south of 2920 South.



1000 West (1290 South to 1700 South)
Construction on a new waterline on the west side of the road will be installed. Construction is anticipated to begin the end of May or beginning of June and be complete by the end of July.

1290 South (1000 West to 1100 West)
Waterline installation and street reconstruction is anticipated to begin mid-May and be complete by the end of July.


1025 West (1290 South to 1475 South)
Curb, gutter, and sidewalk replacements are now in process. Waterline installation and street reconstruction is anticipated to begin the first week in May and be complete by the end of July.



2700 South (500 West to 2000 West)
Construction on the sewer main re-lining will impact traffic in three cities along 2700 South. It is anticipated that impacts in Syracuse will occur beginning August and run through October. Construction will progress westward with left turn restrictions through the construction zone. There are two road closures scheduled: approx 600 West 2700 South in August, and the six-way roundabout in October. These closures will last several days. The travelling public must use caution and follow detour and construction signs. We are grateful to North Davis Sewer District for another project that will rehabilitate our sewer mains.

SR-193: State Street to 2000 West: For information on this UDOT project, use the following contacts:
Hotline: 800-948-4002
Email: sr193@utah.gov
www.udot.utah.gov/sr193
twitter.com/sr193
A recent news article indicates this will be completed by Summer 2014. News Article